Localization Production Tracking

A 40,000 file voice-over localization project for 8 territories, split into batches that move through five stages. The plan sets dates and costs for every batch, stage and territory. Production data is compared against it to show where the project stands on time and money, down to a single territory and stage.

Territories
Status atW37today

Risk flags

Raised automatically from the thresholds below. Worst first.

    Territory scorecard

    Click a row to focus on that territory.

    Territory and stage performance

    Files completed, plan against actual

    Cost and earned value

    Planned value (budget by week) Earned value (budget of work done) Actual cost Forecast cost

    How to read the KPIs

    SPI, schedule performance: budget of the work done divided by the budget of the work planned by now. Below 1 means behind.

    Schedule variance in weeks: how far the work done is from where the plan expected it, in weeks (earned schedule). Negative means behind.

    CPI, cost performance: budget of the work done divided by what it actually cost. Below 1 means over budget. QA weeks with nothing to test count as cost with no work done.

    Forecast cost: actual cost so far, plus the remaining work at its planned cost adjusted by each territory and stage's CPI so far, plus QA team weeks until the forecast delivery.

    Weeks late per stage: forecast end of the batch the stage is working on, against its planned end. It includes delay inherited from earlier stages.

    Weeks lost per stage: actual minus planned durations. It only counts delay the stage created itself, which is what points at the vendor or team to talk to.

    Flag thresholds

    !Watch 1 week lost in a stage, CPI below 0.95, or 3 QA team weeks idle.

    !At risk 2 weeks lost, CPI below 0.90, a QA batch held up, or delivery forecast 1 week after the plan.

    ✕Critical 4 weeks lost or more, CPI below 0.85, or delivery 2 or more weeks after the plan.

    ✓Ahead At least 2 weeks gained in a stage, or ahead of plan overall.

    How this scenario was generated